S5 Geography river landforms practice 3: costing, risk and benefit of flood schemes
- 2026-11-18
S5 Geography river landforms practice 3: costing, risk and benefit of flood schemes
Ten challenge items comparing payback and benefit-cost ratios, reservoir siltation and sediment trapping, return periods, urban peak rises and detention basin capacity.
S5 Geography river landforms practice: evaluating flood schemes This paper puts flood works into a decision setting: payback and benefit-cost comparison of hard and soft schemes, sediment trapping and storage loss, return periods from a flood record, urban versus rural runoff, peak rise under urbanisation, detention basin duration and channel overload. The final item shows embankments transfer rather than remove risk.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 |
| Suggested time | 25 |
| Difficulty mix | Foundation 4 · Intermediate 2 · Challenge 2 · Error redo 2 |
| Chapter | Chapter: S5 Geography: river landforms and flood management |
| Level | Challenge |
02 Questions (10 items)
- FoundationScheme A costs $120m and cuts losses by $15m a year; Scheme B costs $60m and cuts $5m a year. Which pays back sooner?
- FoundationA reservoir traps 85% of incoming sediment. With 4,000 tonnes a year entering, how much passes downstream?
- FoundationA reservoir of 200 million m³ loses 12% of its capacity to siltation in 30 years. How much capacity is lost?
- FoundationEight floods exceeded the warning level between 1920 and 2020. What are the return period and annual probability?
- IntermediateUrban runoff coefficient is 0.85 and rural 0.25. For 100 mm of rain, how much more runoff does the urban area produce and by what factor?
- IntermediateAfter 40% of a catchment is urbanised, peak discharge rises from 200 m³/s to 310 m³/s. What is the increase?
- ChallengeA detention basin holds 80,000 m³ and inflow exceeds outflow by 12 m³/s. How long can it buffer the flood?
- ChallengeSoft engineering (afforestation plus wetland) costs $20m and yields $80m of benefit. What is the benefit-cost ratio?
- Error redoChannel capacity is 250 m³/s but the peak is 340 m³/s. By what percentage is it exceeded, and how much must be diverted?
- Error redoError item: a student says embankments only reduce flood risk. What is the fuller judgement?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | Scheme A: 8 years, against 12 years for B | 120 ÷ 15 = 8; 60 ÷ 5 = 12. |
| 2 | 600 tonnes | 4,000 × (1 − 0.85). |
| 3 | 24 million m³ | 2 × 10⁸ × 0.12. |
| 4 | 12.5 years and 8% a year | 100 ÷ 8 = 12.5; 8 ÷ 100 = 8%. |
| 5 | 60 mm more, i.e. 3.4 times | 85 − 25 = 60; 85 ÷ 25 = 3.4. |
| 6 | 55% | (310 − 200) ÷ 200 × 100. |
| 7 | About 6,667 seconds, i.e. 1.85 hours | 80,000 ÷ 12 ≈ 6,667 s. |
| 8 | 4 (four dollars of benefit per dollar spent) | 80 ÷ 20 = 4. |
| 9 | Exceeded by 36%; 90 m³/s must be diverted | (340 − 250) ÷ 250 × 100 ≈ 36%; 340 − 250 = 90. |
| 10 | Wrong; embankments transfer risk — water is held higher and a breach is far worse | Flood works redistribute risk rather than remove it. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.
Download the full ten-item paper as a PDF, answers and notes included.Tutor Registration →
Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.