S5 ICT | System Development Life Cycle Practice Paper 3
- 2026-11-03
S5 ICT | System Development Life Cycle Practice Paper 3
Paper 3 tests cost and risk judgement: late defect costs, expected loss, schedule reserves, peak load and five-year cost.
Attempt first, mark afterwards Allow about twenty-five minutes; set out cost formulas before substituting, and multiply probabilities to get expected values.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 items |
| Suggested time | About 25 minutes |
| Difficulty mix | Foundation 4 · Intermediate 3 · Challenge 2 · Error redo 1 |
| Chapter | Chapter: S5 ICT | System Development Life Cycle Tutor Prep Guide |
| Level | S5 (Secondary 5) ICT |
02 Questions (10 items)
- FoundationWhat is the biggest cost when a direct cutover fails?
- FoundationWhich of these is a non-functional requirement: adding a loyalty points feature, showing fifty rows per report page, adding a refund button, or allowing receipt uploads?
- FoundationWhat is scope creep?
- FoundationWhich of these is system maintenance rather than new development?
- IntermediateFixing a defect after release costs 2,000 dollars but only 200 dollars at design stage; how much extra is paid when ten defects are found late?
- IntermediateOne extra month of parallel running costs 25,000 dollars; direct cutover fails with probability 20 percent and would cost 200,000 dollars. Which is safer?
- IntermediateA project needs 8 weeks to build, 4 to test and 2 to deploy; how many weeks must be reserved before go-live?
- ChallengeA system handles 12,000 transactions a day, and a three-hour peak carries 60 percent of the load; what is the average per hour at peak?
- ChallengeOn-premise servers cost 18,000 dollars a year to run plus 60,000 dollars upfront; cloud costs 1,800 dollars a month. What is the five-year difference?
- Error redoA student believes go-live ends the project; what is the correct view?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | There is no old system to fall back on, so operations stop at once | That is why direct cutover suits only small or low-risk systems. |
| 2 | Showing fifty rows per report page | The other three say what the system does; this one says how well it does it. |
| 3 | Requirements keep being added without control, pushing time and cost past budget | Each addition looks small, but together they overturn the original plan. |
| 4 | Fixing a program error found after the system went live | Maintenance covers corrective fixes, adapting to environment changes and performance tuning. |
| 5 | 18,000 dollars | Each defect costs 1,800 dollars more, so ten defects add 18,000 dollars. |
| 6 | Parallel running, since 25,000 dollars is below the expected loss of 40,000 dollars | The expected loss is 200,000 times 0.2, which is 40,000 dollars and above the parallel cost. |
| 7 | 14 weeks, which is 98 days | 8 plus 4 plus 2 gives 14 weeks, and 14 times 7 gives 98 days. |
| 8 | 2,400 transactions | 12,000 times 0.6 gives 7,200, and dividing by three hours gives 2,400 per hour. |
| 9 | On-premise 150,000 dollars versus cloud 108,000 dollars, so cloud is 42,000 dollars lower | On-premise is 18,000 times five plus 60,000, while cloud is 1,800 times twelve times five. |
| 10 | Go-live starts maintenance and review, which often takes a large share of total cost | Go-live is the start of delivery, and the longest phase follows it. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.