S6 ICT: system development life cycle (intermediate)

S6 ICT: system development life cycle (intermediate)

  • 2026-11-20

S6 ICT: system development life cycle (intermediate)

Next step: agile and Scrum, sprint points converted to hours, return on investment, defect density and conversion strategies.

Intermediate: agile, sprints and conversion Waterfall freezes requirements before building, while agile slices delivery into short sprints that each ship working software. The three Scrum roles divide the work: the product owner orders the backlog, the Scrum Master removes obstacles, and the team delivers. Points are relative estimates, so converting them to hours needs the team own rate; this paper turns 270 points into 1,620 hours at six hours each, then shows a five-person team at 800 hours a month finishing in about 2.02 months. Parallel, direct, pilot and phased conversion are weighed with the extra running cost worked out.

01 Paper details (check answers afterwards)

Item Detail
Questions 10
Suggested time 25
Difficulty mix Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1
Chapter Chapter: S6 ICT: Object-Oriented Programming and Debugging
Level Intermediate (10 items)

02 Questions (10 items)

  1. FoundationWhat are the three fundamental differences between agile development and waterfall?
  2. FoundationWhich three roles does Scrum define?
  3. Foundation6 sprints of 2 weeks each: how many weeks and days, and how many story points at 45 points per sprint?
  4. IntermediateA backlog of 300 points at 45 points per sprint needs how many sprints, how many extra weeks over the planned 6, and how many points in the last sprint?
  5. Intermediate270 points at 6 hours per point is how many hours, and how many months for 5 people at 8 hours a day and 20 days a month?
  6. IntermediateA system returns $900,000 against a $600,000 development cost. What is the return on investment?
  7. ChallengeTesting finds 240 defects and 60 more appear in production on a 40 KLOC system. What is the defect density?
  8. ChallengeA parallel conversion runs both systems for 2 months at $40,000 a month each. What is the extra cost?
  9. ChallengeWhat is the order of the four testing levels from smallest to largest?
  10. Error redoA burn-down of 240 points over 6 sprints gives 40 points per sprint ideally; after 4 sprints 120 points are done, leaving 120. How far behind is the team?

03 Answers and one-line notes

# Answer One-line note
1 Iterative delivery of working software, treating requirement change as normal, and measuring progress by working software rather than documents. Agile does not lack process; it shortens the feedback cycle from months to weeks.
2 Product owner, Scrum Master, and the development team. The product owner decides what, the Scrum Master keeps the process flowing, and the team delivers.
3 12 weeks, that is 84 days, delivering 270 points. Story points are relative estimates, not hours.
4 7 sprints, that is 14 weeks, 2 weeks more; the last sprint carries 30 points. Round up when there is a remainder; 6.7 sprints is not an answer.
5 1620 hours; with 800 hours a month that is about 2.02 months. Converting points to hours needs the team own rate, otherwise the estimate means nothing.
6 ROI is (900,000 minus 600,000) divided by 600,000, that is 50.0 percent. ROI is divided by cost, not by benefit; using the wrong denominator doubles the figure.
7 Density is 240 divided by 40, that is 6.0 defects per KLOC. Defect density divides by code size so projects can be compared.
8 An extra $80,000, the two months of duplicated running cost. Parallel running is safest and costliest; direct cut-over is cheapest and riskiest.
9 Unit testing, integration testing, system testing, then acceptance testing. Each level must pass before moving up; skip integration and system testing turns into a debugging session.
10 Ideal remainder is 80 points against an actual 120, so the team is 40 points behind. Read the trend rather than one point; two or three sprints behind means scope must be adjusted.

04 What to do after marking

  • After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
  • Repeat the same item two days later; move to the next paper only when both attempts are correct.
  • Parents only need the answer and note columns; there is no need to explain every item.

Want the five SDLC phases, the waterfall versus agile trade-off, and person-days, payback and defect density all straightened out? Book a TutorZone tutor and settle every number in twenty-five minutes.Tutor Registration →