Challenge: COCOMO, function points, defect removal efficiency, availability, risk exposure and earned value.
Challenge: estimation, metrics and earned value Managing a project takes numbers, not feelings. COCOMO estimates effort from size, and an exponent above one means doubling size more than doubles effort; function points weight five component types and adjust them with fourteen factors. Quality is measured by defect removal efficiency, availability and coverage; risk ranks by probability times impact, so a total exposure of 130,000 is the buffer to hold. Earned value puts schedule and cost on one sheet: SPI 0.80 with CPI 0.89 means late and over budget at once, so 562,500 is the honest forecast of the final cost.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 |
| Suggested time | 25 |
| Difficulty mix | Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1 |
| Chapter | Chapter: S6 ICT: Object-Oriented Programming and Debugging |
| Level | Challenge (10 items) |
02 Questions (10 items)
- FoundationIn basic organic COCOMO with E = 2.4 times KLOC to the power 1.05, what effort in person-months does a 10 KLOC project need?
- FoundationFor the same project, D = 2.5 times E to the power 0.38. What duration does that give?
- FoundationFunction points: 6 external inputs at 4 each, 4 external outputs at 5, 3 queries at 4, 3 internal logical files at 10 and 2 external interface files at 7. What is the UFP, and the AFP at TDI 42?
- IntermediateTesting finds 200 defects and 40 escape to production. What is the defect removal efficiency?
- IntermediateWith MTBF of 4,000 hours and MTTR of 2 hours, what is availability?
- IntermediateThree risks: probability 0.3 with a $200,000 impact, 0.1 with $500,000, and 0.5 with $40,000. What is total risk exposure?
- ChallengeWith PV $200,000, EV $160,000, AC $180,000 and BAC $500,000, what are SPI, CPI and EAC?
- ChallengeA flow graph has 12 edges, 10 nodes and 1 connected component. What is the cyclomatic complexity?
- ChallengeA system has 1,200 statements and tests execute 1,020 of them. What is statement coverage?
- Error redoA team writes 24,000 lines in 120 person-days. What is the productivity per person-day, and the effort for 30,000 lines?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | E is 2.4 times 10 to the power 1.05, about 26.9 person-months. | An exponent above one means effort grows faster than size; double the size is more than double the work. |
| 2 | D is about 8.7 months. | Duration is not proportional to effort; adding people shortens schedules only up to a point. |
| 3 | UFP is 100 and AFP is 107.0. | The adjustment factor stays between 0.65 and 1.35 and cannot be stretched at will. |
| 4 | DRE is 200 divided by 240, about 83.3 percent. | The denominator is total defects including escapes, not just those found. |
| 5 | Availability is 4,000 divided by 4,002, about 99.95 percent. | Availability is a time ratio, not a claim that failures are rare. |
| 6 | The total is $130,000. | Risk exposure multiplies probability by impact to rank risks, not to forecast the actual loss. |
| 7 | SPI is 0.80, CPI is 0.89 and EAC is $562,500. | Both indices below one mean late and over budget; EAC projects the final cost through CPI. |
| 8 | CC is 12 minus 10 plus 2, that is 4. | Cyclomatic complexity equals the number of independent paths, hence the minimum tests for branch coverage. |
| 9 | 1,020 divided by 1,200 gives 85.0 percent. | Coverage can never exceed 100 percent; above that means the denominator is wrong. |
| 10 | 200 lines per person-day, so 30,000 lines need 150 person-days. | Compare productivity within one team and language; lines of code across languages mean nothing. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.