S6 ICT System Testing and Acceptance Practice 3 (Challenge)
- 2026-11-18
S6 ICT System Testing and Acceptance Practice 3 (Challenge)
Ten items cover acceptance criteria, alpha and beta testing, branch coverage, automation savings, leakage rate and defect convergence.
Acceptance criteria and defect analysis Challenge items mix percentages with time units, so unify units before comparing.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 |
| Suggested time | 25 |
| Difficulty mix | Foundation 4 · Intermediate 2 · Challenge 2 · Error redo 2 |
| Chapter | Chapter: S6 ICT: system testing and acceptance |
| Level | Challenge |
02 Questions (10 items)
- FoundationWhen should acceptance criteria be agreed with the customer?
- FoundationHow do the locations of alpha and beta testing differ?
- FoundationDoes 100 percent statement coverage mean every branch has been executed?
- FoundationA function has four equivalence classes and two test values are taken from each. How many test values in total?
- Intermediate800 regression cases take 2 minutes each by hand and 10 seconds each when automated. What percentage of time is saved?
- IntermediateTesting finds 108 defects and users find 12 more after delivery. What is the defect leakage rate?
- ChallengeThree test rounds find 60, 24 and 9 defects. By what percentage did the third round fall compared with the first?
- Challenge24 defects take 3 person-hours each to fix. How many hours does a team of two need?
- Error redoA student thinks beta testing happens in a laboratory. What is correct?
- Error redoDoes a 100 percent pass rate mean the system has no defects?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | Before development starts. | Agreeing criteria up front avoids disputes about what counts as finished at handover. |
| 2 | Alpha runs at the developer site with internal staff, beta runs in real user environments with users. | Both are user-level tests carried out before handover. |
| 3 | No. | Statement coverage does not guarantee both sides of every decision, so branch coverage is needed as well. |
| 4 | Eight. | Multiply the number of equivalence classes by the values taken from each class. |
| 5 | About 91.7 percent. | Manual runs cost 1600 minutes and automation about 133.3 minutes, which gives the saving. |
| 6 | 10 percent. | Leakage is defects found after delivery divided by all defects. |
| 7 | 85 percent. | Fast convergence of defect counts shows the system is stabilising and helps decide when to exit testing. |
| 8 | 36 hours. | The total is 72 person-hours, divided by two people. |
| 9 | Beta testing runs in real user environments, while laboratory testing is alpha testing. | Different environments surface different kinds of defects. |
| 10 | Not necessarily. | Test cases may not cover every situation, and uncovered parts can still hide defects. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.
Download the full ten-item paper as a PDF, answers and notes included.Tutor Registration →
Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.