A-Level Business: Operations and Project Management, Capacity, Inventory, Lean, Quality and the Critical Path (lesson-prep guide for tutors)
- 2026-11-25
Students assume more capacity is always better, divide holding cost by the whole order instead of the average stock, and look for the longest line on a network without working out float. This chapter fixes three things: capacity utilisation divides by design capacity, EOQ uses average stock, and the critical path is the line with zero float.
01 Prerequisites (3-minute check)
If any of these fails, fix it before the lesson starts.
| Skill | Quick check | Pass mark |
|---|---|---|
| Percentages | Actual output of 17,000 against design capacity of 20,000. What percentage is used? | 85 per cent, that is 17,000 over 20,000 |
| Average stock | An order of 3,000 units is used up steadily. What is the average stock? | Half, which is 1,500, because stock falls from 3,000 to zero |
| Square roots | What is the square root of 9,000,000? | 3,000, the last step of the EOQ formula |
| Adding paths | Two paths merge into one activity. When can it start? | When both are finished, so take the later one |
02 Lesson flow (60 minutes)
| Time | Stage | Tutor does | Student does |
|---|---|---|---|
| 0-6 min | Opening check | Ask whether more capacity is always better and more stock always safer | Name the cost on both sides |
| 6-16 min | Capacity and methods | Utilisation, outsourcing, overtime, set-up cost per unit | Calculate 85 per cent and the cost of three responses |
| 16-28 min | Inventory and EOQ | Buffer, lead time, reorder level, EOQ, stock graphs | Calculate 3,000 units and 700 |
| 28-40 min | Lean and quality | JIT, kaizen, kanban, TQM, benchmarking, total quality cost | Calculate a net saving of 36,000 |
| 40-52 min | Network and critical path | Earliest start, latest finish, float, critical path, crashing | Find 14 days and 2 days of float |
| 52-60 min | Exit check | Three questions, set the homework | Work independently |
03 Teaching script (read it out)
Scene 1: Capacity and production methods: utilisation has a ceiling and a floor
Demand rises to 21,000, which is 1,000 above output. Three responses must be costed: outsource 1,000 units at 45 against an in-house 32, a premium of 13 each and 13,000 a week, but no capital is needed; overtime uses existing equipment at the cost of premium pay and fatigue; expansion needs capital and time but gives the lowest long-run unit cost. Ask students to choose one for a rush order, one for a permanent rise and one for a cash-poor firm.
Production methods compare set-up cost per unit: job production sets up at 400 for 20 units, which is 20 each; batch production sets up at 900 for 500, which is 1.8; flow production spends 40,000 over 100,000 units, which is 0.4. Larger batches cut set-up cost per unit but raise stock and cut flexibility, and students should state that trade-off themselves. Productivity follows: 25 workers times 8 hours times 5 days gives 1,000 labour hours, so 17,000 units is 17 per hour; lean improvement lifts output to 18,700, which is 18 per hour and 10 per cent.
Link capacity to break-even: fixed costs of 680,000 a week and contribution of 40 a unit give a break-even of 17,000 units, exactly 85 per cent of design capacity. The plant must run at 85 per cent just to cover costs; if contribution falls to 34, break-even rises to 20,000 units, which is 100 per cent and leaves no cushion at all.
Student task: cut the outsourcing price from 45 to 42 and recalculate the premium per unit (10) and the weekly cost (10,000), then say whether expansion is still justified.
A sentence you can read aloud: The denominator of utilisation is design capacity, not demand and not maximum capacity.
Scene 2: Inventory, lean and quality: total cost first, ideas second
Economic order quantity balances two costs: ordering and holding. The formula is the square root of two times annual demand times order cost, divided by holding cost per unit per year. With demand of 36,000, an order cost of 500 and holding of 4, EOQ is 3,000 units and the firm orders 12 times a year. Ordering costs 12 times 500, which is 6,000; holding costs average stock of 1,500 times 4, which is 6,000; the total is 12,000. An order of 2,000 gives ordering of 9,000 and holding of 4,000, a total of 13,000, which is 1,000 worse. Students should say that EOQ is not the lowest stock, it is the lowest combined cost.
Lean production pushes stock down: from 3,000 to 500 units, holding cost falls from 12,000 to 2,000 and saves 10,000. But JIT needs reliable suppliers, stable transport and predictable demand, and one break stops the line; kaizen relies on continuous improvement by everyone, kanban on pull production and cell production on small teams finishing a whole item. Every tool must be presented with its cost as well as its benefit.
Quality management has three levels: inspection catches defects at the end, quality assurance writes standards into the process, and TQM makes everyone responsible. The numbers: annual output of 50,000 at 4 per cent defects is 2,000 units, and at 60 each the cost is 120,000; TQM cuts defects to 1 per cent, which is 500, and cost to 30,000, saving 90,000 against a programme cost of 54,000 for a net 36,000. A benchmark of 0.8 per cent, which is 400 units, would save a further 6,000.
Student task: raise rework cost from 60 to 75 and recalculate the cost before and after TQM (150,000 and 37,500) and the net saving (58,500).
A sentence you can read aloud: EOQ is not the least stock, it is the least combined ordering and holding cost.
Scene 3: Project management: the critical path is the line with zero float
Push latest finishes right to left: E must finish by day 14 and start by day 12; D must finish by day 12; B and C must finish by day 7 and 7; A must satisfy both B and C, so it must finish by day 3. Float is latest start minus earliest start: A has 0, B has 0, C has 2, D has 0 and E has 0. The zero-float activities join into the critical path A-B-D-E at 14 days, while C can start up to 2 days late without moving the end date.
Crashing only applies to critical activities, and the cheapest day to buy is the one to buy. Cutting D from 5 to 3 days at 4,000 a day costs 8,000 and shortens the project from 14 to 12 days. Redraw afterwards: the C path is 3 plus 2 plus 3, which is 8 days, still below 12, so the critical path has not moved.
Student task: extend E from 2 to 5 days and recalculate the project duration (17 days) and the float on C (still 2 days), then say whether the critical path changes.
A sentence you can read aloud: The critical path is the line of zero float, and crashing applies only to activities on it.
04 Question types and worked steps
| Type | Example | Steps | Answer |
|---|---|---|---|
| Capacity utilisation | Design 20,000 and actual 17,000 | Actual output over design capacity | 85 per cent |
| EOQ | Demand 36,000, order cost 500, holding 4 | Square root of two times demand times order cost over holding cost | 3,000 units over 12 orders |
| Reorder level | Daily usage 100, lead time 5, buffer 200 | Lead-time demand plus buffer | 700 units |
| Quality cost | 50,000 units, defects from 4 to 1 per cent at 60 each | Defective units times rework cost, compared across periods | From 120,000 down to 30,000 |
| Critical path | A 3, B 4, C 2, D 5, E 2 days | Earliest starts left to right, latest finishes right to left, zero float joined | A-B-D-E at 14 days, C with 2 days of float |
| Set-up per unit | Job 400 for 20, batch 900 for 500 | Set-up cost divided by batch size | 20 and 1.8 |
05 Independent practice (3 questions)
| Question | Answer | What to watch |
|---|---|---|
| Design capacity of 20,000 units and output of 17,000. Find utilisation, and the weekly extra cost of outsourcing 1,000 units at a premium of 13. | 85 per cent and 13,000 | Divide by design capacity, then multiply the premium by the shortfall |
| Annual demand of 36,000, order cost of 500 and holding cost of 4 per unit per year. Find EOQ, orders per year and total stock cost. | 3,000 units, 12 orders, 12,000 in total | Square root, then divide demand by EOQ; ordering and holding are equal at the optimum |
| A takes 3 days, B takes 4 after A, C takes 2 after A, D takes 5 after B and C, E takes 2 after D. Find the duration, the critical path and the float on C. | 14 days, A-B-D-E, C with 2 days of float | Earliest starts left to right, latest finishes right to left, then subtract |
06 Common mistakes and what to say
| Mistake | Student writes | Say this |
|---|---|---|
| Dividing actual output by demand | Writing 17,000 over 21,000 to get 81 per cent | The denominator is design capacity of 20,000, which gives 85 per cent. |
| Using the whole order for holding cost | Writing 3,000 times 4 to get 12,000 | Average stock is 1,500, so holding cost is 6,000. |
| Reading float off the wrong pair | Writing 5 days for D | Float is latest start minus earliest start, which is 0 for D; latest finish minus earliest finish is a different line. |
| Assuming TQM must raise cost | Quoting the 54,000 programme and stopping there | Compare total quality cost: 90,000 saved gives a net 36,000. |
07 Homework (paper, section and question numbers)
- A-Level Business chapter index — Every chapter in this subject
- All prep guides — The same series in other subjects
- Redo this chapter — Practice 1 to 3: utilisation, EOQ, critical path
08 Exit check (last 5 minutes)
| Question | Answer | Decision |
|---|---|---|
| One denominator | Utilisation divides by design capacity | Dividing by demand means scene one again |
| One average | EOQ holding uses average stock of Q over two | Using the whole order means scene two again |
| One line | The critical path joins the zero-float activities | Finding only the longest leg means scene three again |
09 Tutor FAQ
Is one hundred per cent utilisation best?
No. At full capacity there is no time for preventive maintenance, breakdowns or rush orders, so quality and delivery risk rise. Most plants keep five to fifteen per cent of headroom, with the exact figure set by equipment reliability and demand variability.
Does JIT mean zero stock?
No. JIT squeezes stock to a minimum but keeps a buffer, because suppliers can be late, transport can be disrupted and demand can jump. JIT needs reliable suppliers, stable quality and predictable demand, or the saving in holding cost turns into lost output when the line stops.
Which activity should be crashed?
Only one on the critical path, and the one with the lowest cost per day saved. The network must then be redrawn, because a path that had float can become the new critical path, and only then is crashing it useful.
Find a tutor — freeTutor Registration →
A TutorZone lesson-prep guide. Written by the TutorZone team; questions and lesson flow are original and are not taken from any school or publisher material.