Industrial system and location: ten challenge items

Industrial system and location: ten challenge items

  • 2026-11-18

Industrial system and location: ten challenge items

Compare the total cost of three sites, work out output per worker and the break-even point, then decide with a weighted score.

Why can a location decision not rest on one cost item? Because total cost mixes materials, labour, transport, land and energy; the cheapest on one item need not be cheapest overall, so compare total cost or a weighted score.

01 Paper details (check answers afterwards)

Item Detail
Questions 10
Suggested time 25
Difficulty mix Foundation 4 · Intermediate 2 · Challenge 2 · Error redo 2
Chapter Chapter: S2 Geography: Industrial system and industrial location
Level Challenge

02 Questions (10 items)

  1. FoundationCost per item: A has $40 material, $30 labour, $10 transport; B has $30, $45, $8; C has $35, $25, $25. Which site has the lowest total cost?
  2. FoundationIf all transport charges rise 20%, what is the total cost per item at A and at B?
  3. FoundationLabour is 45% of total cost and wages rise 8%. By how much does total cost rise?
  4. FoundationAutomation cuts the workforce from 200 to 50. What is the reduction?
  5. IntermediateOutput stays at 4,800 items a day. What is output per worker with 200 workers and with 50 workers?
  6. IntermediateFixed cost is $600,000 and each item earns $15 of contribution. How many items break even?
  7. ChallengeA site scores 80 on market, 60 on labour and 70 on transport, with weights 0.4, 0.3 and 0.3. What is the weighted score?
  8. ChallengeA new site costs $72 an item against $78 at the present site. What is the gap as a share of the present cost?
  9. Error redoThe plant discharges 1,200 cubic metres of waste water a day at $8 per cubic metre. What is the daily treatment cost?
  10. Error redoWhy does moving from pure OEM work to own-brand manufacturing raise value added?

03 Answers and one-line notes

# Answer One-line note
1 Site A, at $80 an item. A totals 80, B totals 83 and C totals 85, so only a total cost comparison settles it.
2 A becomes $82 and B becomes $84.6, so A stays the cheapest. Transport rises to $12 and $9.6, so A is 40 plus 30 plus 12 and B is 30 plus 45 plus 9.6.
3 3.6%. 45% times 8% equals 3.6%, so the larger the share, the bigger the effect on total cost.
4 75%. 200 minus 50, divided by 200 and times 100, gives 75%, measured against the original 200.
5 It rises from 24 items to 96 items, four times as much. 4,800 divided by 200 is 24, 4,800 divided by 50 is 96, and 96 divided by 24 is 4.
6 40,000 items. 600,000 divided by 15 equals 40,000, which is the break-even output.
7 71 marks. 80 times 0.4 plus 60 times 0.3 plus 70 times 0.3 gives 32 plus 18 plus 21, which is 71.
8 About 7.7%. 78 minus 72, divided by 78 and times 100, gives 7.7%, with the present cost as the base.
9 $9,600. 1,200 times 8 equals 9,600, which is 2.0% of turnover if turnover is $480,000.
10 Because the firm then controls design, brand and sales, and keeps the margin. Design upstream and branding downstream earn higher margins, while pure subcontracting earns only a processing fee.

04 What to do after marking

  • After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
  • Repeat the same item two days later; move to the next paper only when both attempts are correct.
  • Parents only need the answer and note columns; there is no need to explain every item.

Download the full ten-item paper as a PDF, answers and notes included.Tutor Registration →

Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.