S4 Geography: River Hydrographs, Discharge and Lag Time, from 60 millimetres of rain to 5.25 million cubic metres (worked example) Tutor Prep Guide with a 45-minute plan

S4 Geography: River Hydrographs, Discharge and Lag Time, from 60 millimetres of rain to 5.25 million cubic metres (worked example) Tutor Prep Guide with a 45-minute plan

  • 2026-11-16

Students look at a hydrograph and can only say the line goes up and then down. Asked for the peak, the lag time, or why the urban curve is taller and narrower, they have nothing. They treat discharge and rainfall as the same quantity and cannot tell which part of the curve is surface runoff and which is baseflow. This lesson works one 250 square kilometre catchment from the rainfall arithmetic through the graph to an urban comparison built on the same numbers.

Objectives — By the end of the lesson students can: (1) compute 5.25 million cubic metres of runoff from 60 millimetres of rain, a coefficient of 0.35 and 250 square kilometres, and state how it differs from the 15 million cubic metres of rainfall; (2) read a peak of 180 cubic metres per second, a baseflow of 20 and a lag time of 8 hours from a hydrograph and say which two moments the lag is measured between; (3) compute the ratio of peak to mean excess flow as 2.96 and explain why the peak is so much higher than the mean; (4) explain the three reasons and two consequences when urbanisation raises the coefficient to 0.70, shortens the lag to 4 hours and lifts the peak to 320 cubic metres per second.

01 Prerequisites (3-minute check)

If any of these fails, fix it before the lesson starts.

Skill Quick check Pass mark
Runoff coefficient What does 0.35 mean for the share of rain that becomes runoff About a third, with the rest infiltrating, evaporating or intercepted
Units How many litres of rain fall on one square metre from 60 millimetres 60 litres, or 0.06 cubic metres
Discharge What does 180 cubic metres per second mean 180 tonnes every second, about a third of an Olympic pool each minute
Area How many square metres are in 250 square kilometres 250 million square metres

02 Lesson flow (45 minutes)

Time Stage Tutor does Student does
0-6 min Entry check Where rain goes after landing, what a coefficient of 0.35 means, whether discharge and rainfall are the same thing Spoken answers written into two columns
6-18 min Act one: rainfall to runoff volume 60 millimetres times 250 square kilometres is 15 million cubic metres, times 0.35 is 5.25 million Students work the calculator and write both volumes
18-30 min Act two: three numbers on the graph Baseflow 20, peak 180, lag from a rainfall peak at hour 3 to a discharge peak at hour 11, so 8 hours Students mark all three and write how each is measured
30-40 min Act three: rural against urban Coefficient 0.35 to 0.70, volume 5.25 to 10.5 million, lag 8 to 4 hours, peak 180 to 320 Students name three causes and two consequences
40-43 min Fresh numbers Same catchment, 90 millimetres of rain, coefficient 0.35: find the runoff volume 7.875 million cubic metres while circulating
43-45 min Exit check Three spoken questions: the coefficient, the lag measurement, the urban effects All three correct

03 Teaching script (read it out)

Scene 1: Act one: rainfall is the input, runoff is what the channel actually receives

Separate the two volumes first. Total rainfall is 60 millimetres times 250 square kilometres, so 0.06 metres times 250 million square metres, which is 15 million cubic metres. The channel never receives all of it, because some infiltrates, some evaporates and some is intercepted by leaves, so multiply by 0.35 and the runoff is 5.25 million cubic metres. Students must press the calculator themselves and must write the unit, because million cubic metres and cubic metres differ by a factor of ten thousand, the commonest careless error in the topic. Give one scale comparison: 5.25 million cubic metres is about 2,100 Olympic pools, which turns an abstract figure into a real flood. Close with intensity, since 60 millimetres over 6 hours is 10 millimetres per hour, a catchment-wide input of 694 cubic metres per second, the ceiling used in the next act.

Compute 15 million and 5.25 million cubic metres and show where the coefficient sits in the working.

Scene 2: Act two: a hydrograph only needs three numbers, baseflow, peak and lag

The first number is the baseflow of 20 cubic metres per second, the flow sustained by groundwater before the storm, which is the flat line before the rise. The second is the peak of 180 cubic metres per second at hour 11. The third is the lag, measured from the rainfall peak at hour 3 to the discharge peak at hour 11, which is 8 hours. Be explicit that the lag starts at the rainfall peak, not at the first drop, since students who start at the end of the 6 hour storm answer 5 hours. Then contrast two ratios: the input ceiling of 694 cubic metres per second against an actual peak of 180 gives 0.259, showing storage and delay inside the catchment, and the peak divided by the mean excess flow of 60.76 gives 2.96, showing that one storm leaves the catchment at nearly three times its mean rate. Finally strip the baseflow, because the excess is what the volume arithmetic needs, and mixing the two conventions is the second commonest error.

Point to the rainfall peak, the discharge peak and the baseflow line on the graph, then state which two moments give the lag.

Scene 3: Act three: urbanisation turns the same storm into a taller, narrower graph

Give all three causes in one pass. Impermeable surfaces such as asphalt and roofs cut infiltration to almost nothing, so the coefficient rises from 0.35 to 0.70; drains and storm sewers carry water straight to the channel, shortening the flow path, so the lag falls from 8 hours to 4; together these lift the runoff volume from 5.25 to 10.5 million cubic metres and the peak from 180 to 320 cubic metres per second. Students should describe the graph rather than recite, and the urban curve is taller, narrower and earlier, which is the skeleton of any answer. Then give the consequences, since a peak that arrives fast and high overwhelms the downstream channel, so cities build detention ponds, flood parks and permeable paving precisely to lengthen the lag. Finish with return period, because the third largest flood in a 20 year record has a return period of 21 divided by 3, which is 7 years, turning the phrase once in so many years into arithmetic.

Write the three features of the urban curve, taller, narrower and earlier, each with one cause.

04 Question types and worked steps

Type Example Steps Answer
Runoff volume 60 millimetres, coefficient 0.35, 250 square kilometres: find the volume Rainfall in metres times area times the coefficient Forgetting the coefficient and answering 15 million
Graph reading Find the peak, the baseflow and the lag Peak at the highest point, baseflow on the pre-storm line, lag from peak to peak Measuring the lag from the first rain and answering 5 hours
Peak ratio Find the ratio of peak to mean excess flow Remove the baseflow first, then divide over the storm duration Leaving the baseflow inside the peak
Urbanisation Compare rural and urban curves Coefficient up, lag down, peak up, all three Saying only that there is more water
Sanity check (teach this): Five checks: the runoff volume of 5.25 million must be below the 15 million of rainfall, in the exact ratio of 0.35; the peak of 180 must be below the input ceiling of 694.4, and a peak above the ceiling means water appeared from nowhere; the lag of 8 hours must be shorter than the 24 hour hydrograph, or the time axis was misread; the peak ratio of 2.96 must exceed one, and a value below one means peak and mean were swapped; the urban peak of 320 must be above 180 and the urban lag of 4 below 8, and any reversal means the reasoning has been inverted.

05 Independent practice (3 questions)

Question Answer What to watch
Volume 90 millimetres, coefficient 0.35, 250 square kilometres Whether the rainfall was converted to metres
Graph Mark the peak, baseflow and lag Whether the lag starts at the rainfall peak
Peak ratio Divide 180 by 60.76 Whether the baseflow was removed
Urbanisation Write three features and three causes Whether impermeable surfaces and drains are named

06 Common mistakes and what to say

Mistake Student writes Say this
Omitting the coefficient Answering 15 million cubic metres of runoff Fifteen million is the rainfall total, and the channel does not collect all of it. Infiltration, evaporation and interception come off first, so 0.35 gives 5.25 million. Answering 15 million claims the hillside absorbs nothing.
Wrong lag start Answering a lag of 5 hours The lag is the gap between the rainfall peak and the discharge peak, hour 3 to hour 11, which is 8 hours. Measuring from the end of the storm at hour 6 answers a different question.
Baseflow left inside Answering a peak of 200 or a ratio of 3.3 The 180 on the graph already includes the 20 of baseflow, so the excess peak is 160. Be consistent: strip it from both sides or from neither, never one.
Urbanisation without timing Answering that cities flood because there is more water The point is not only more, it is faster. The urban runoff is 10.5 million cubic metres with a lag of 4 hours and a peak of 320, so the channel cannot drain in time. Name taller, narrower and earlier.

07 Homework (paper, section and question numbers)

08 Exit check (last 5 minutes)

Question Answer Decision
Runoff volume 60 millimetres times 250 square kilometres times 0.35 is 5.25 million cubic metres Answering 15 million means act one
Lag time Hour 11 minus hour 3 is 8 hours Starting at the first rain means act two
Urban effects Coefficient 0.70, lag 4 hours, peak 320 Only saying more water means act three

09 Tutor FAQ

Do students memorise a runoff coefficient?

No single value, but they should know rural land is roughly 0.2 to 0.4 and urban land can reach 0.7 to 0.9, and explain the gap with impermeable cover.

How is return period calculated?

By the Weibull expression, record years plus one divided by rank. The largest flood in 20 years is a 21 year event and the third largest is 7 years, an expected frequency rather than a guarantee.

Why teach the peak ratio?

It turns the shape of a hydrograph into a number, and the urban consequence is precisely a larger peak ratio, which compares better than repeating the words taller and narrower.

Find a tutor — freeTutor Registration →

A TutorZone lesson-prep guide. Written by the TutorZone team; questions and lesson flow are original and are not taken from any school or publisher material.

Join as a tutor or coach — academic, music, sports, arts, STEM. Free to register. See how it works →