S6 Geography | Energy Resource Management Practice Paper 3 (Challenge)
- 2026-11-03
S6 Geography | Energy Resource Management Practice Paper 3 (Challenge)
Think like a planner: reserve margin, storage hours, emissions and carbon cost, then the debates on carbon tax, green hydrogen and life-cycle assessment.
Attempt first, mark afterwards Allow about thirty-five minutes; state assumptions and units, do the arithmetic, then add one line on the policy meaning.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 items |
| Suggested time | About 35 minutes |
| Difficulty mix | Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1 |
| Chapter | Chapter: S6 Geography | Energy Resource Management |
| Level | S6 (Secondary 6) Geography |
02 Questions (10 items)
- FoundationPeak demand is 6 GW and the reserve margin is 20 per cent. How much installed capacity is needed?
- FoundationWhy is comparing wind, solar and nuclear by capacity factor alone unfair?
- IntermediateA battery stores 400 MWh with 100 MW of power. How long can it discharge at full power?
- IntermediateA factory uses 2 GWh a year and the grid emits 0.6 kg CO2 per kWh. What are its annual emissions?
- IntermediateIf those emissions must fall by 35 per cent, what is the target?
- ChallengeWith a carbon price of 50 dollars a tonne, what is the factory annual carbon cost?
- ChallengeWhat are the main weaknesses of a carbon tax and of renewable subsidies?
- ChallengeWhat is the main bottleneck of green hydrogen as a storage medium?
- FoundationWhich three stages must a life-cycle comparison of energy sources cover?
- Error redoIs the statement that nuclear power is zero carbon accurate?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | 7 200 MW | 6 000 times 1.2 equals 7 200 MW; the margin covers maintenance and forced outages. |
| 2 | Nuclear is dispatchable baseload, while wind and solar depend on weather and need backup or storage | A fair comparison also weighs dispatchable capacity, system integration cost and emissions cut. |
| 3 | 4 hours | 400 MWh divided by 100 MW equals 4 hours, which decides whether it can cover the evening peak. |
| 4 | 1 200 tonnes | 2 000 000 kWh times 0.6 is 1 200 000 kg, that is 1 200 tonnes. |
| 5 | 780 tonnes | 1 200 times 0.65 equals 780 tonnes, a cut of 420 tonnes a year. |
| 6 | 60 000 dollars | 1 200 times 50 is 60 000 dollars, falling to 39 000 if emissions drop to 780 tonnes. |
| 7 | A tax is politically unpopular and hits low-income groups harder; subsidies strain the budget and invite rent seeking | Either way, grid and storage investment is needed or the price signal will not cut emissions. |
| 8 | Round-trip efficiency through electrolysis, compression, transport and re-generation is only about one third | Green hydrogen therefore suits hard-to-electrify heavy industry and shipping rather than ordinary storage. |
| 9 | Fuel extraction or equipment manufacture, operation, and decommissioning with waste handling | Counting operating emissions alone understates the embodied carbon of solar and nuclear. |
| 10 | Not quite: operation is near zero, but uranium mining, enrichment, construction and waste handling emit | The accurate wording is low-carbon in operation, with a measurable whole-life footprint. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.