S6 ICT: project management and scheduling (intermediate)

S6 ICT: project management and scheduling (intermediate)

  • 2026-11-20

S6 ICT: project management and scheduling (intermediate)

Intermediate: comparing path lengths, total float and latest start, crash savings, then schedule and cost performance indices.

Intermediate: critical path and performance indices The second paper puts numbers on the network. A takes 4 days, B 6, C 3 and D 5, so the two paths run 15 and 12 days; the longer A to B to D is critical at 15 days. Task C has 3 days of total float: an earliest start of day 4 and, working back from the finish, a latest start of day 7. Crashing B from 6 to 4 days brings the duration to 13, a saving of 13.33 percent. On performance, planned value of 100,000 against earned value of 80,000 gives an index of 0.8, while actual cost of 90,000 gives a cost index of 0.89. It ends on peak headcount and the definition of the critical path.

01 Paper details (check answers afterwards)

Item Detail
Questions 10
Suggested time 25
Difficulty mix Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1
Chapter Chapter: S6 ICT: Project Management and Scheduling
Level Intermediate (10 items)

02 Questions (10 items)

  1. FoundationTasks A, B and D take 4, 6 and 5 days in series. How long is that path?
  2. FoundationThe same network also has a path A to C to D with C at 3 days. How long is that path?
  3. FoundationWhich path is critical and what is the project duration?
  4. IntermediateWhat is the total float of task C?
  5. IntermediateTask C has an earliest start of day 4. What is its latest start?
  6. IntermediateCrashing task B from 6 to 4 days changes the duration to what, and by what percentage?
  7. ChallengePlanned value is 100,000 dollars and earned value 80,000 dollars. What is the schedule performance index and what does it mean?
  8. ChallengeActual cost is 90,000 dollars. What is the cost performance index?
  9. Challenge5 tasks run at the same time, each needing 2 people. What is the peak headcount?
  10. Error redoError item: a student says the critical path is the shortest path in the network. What is wrong?

03 Answers and one-line notes

# Answer One-line note
1 15 days. 4 plus 6 plus 5 gives 15.
2 12 days. 4 plus 3 plus 5 gives 12.
3 A to B to D is critical and the duration is 15 days. The longest path wins, and 15 exceeds 12, so the project runs 15 days.
4 3 days. The critical path minus the path through C is 15 minus 12, giving 3.
5 Day 7. Working back from the finish, 15 minus 5 minus 3 gives 7.
6 13 days, a cut of 2 days or 13.33 percent. 4 plus 4 plus 5 gives 13; the saving over 15 is 13.33 percent.
7 0.8, meaning the project is twenty percent behind schedule. The index is 80000 over 100000, or 0.8; below one means slipping.
8 0.89, so each dollar spent returns only 0.89 dollars of value. The index is 80000 over 90000, or 0.89; below one means overspending.
9 10 people. 5 times 2 gives 10, which feeds resource levelling.
10 Wrong. The critical path is the longest path and it carries zero total float. Mixing up the longest duration with the shortest path leads to crashing the wrong task.

04 What to do after marking

  • After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
  • Repeat the same item two days later; move to the next paper only when both attempts are correct.
  • Parents only need the answer and note columns; there is no need to explain every item.

Want every float value on the network diagram worked out cell by cell? Book a TutorZone tutor and unpack all ten items with the critical path in 25 minutes.Tutor Registration →

Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.

Join as a tutor or coach — academic, music, sports, arts, STEM. Free to register. See how it works →