S6 ICT: project management and scheduling (intermediate)
- 2026-11-20
S6 ICT: project management and scheduling (intermediate)
Intermediate: comparing path lengths, total float and latest start, crash savings, then schedule and cost performance indices.
Intermediate: critical path and performance indices The second paper puts numbers on the network. A takes 4 days, B 6, C 3 and D 5, so the two paths run 15 and 12 days; the longer A to B to D is critical at 15 days. Task C has 3 days of total float: an earliest start of day 4 and, working back from the finish, a latest start of day 7. Crashing B from 6 to 4 days brings the duration to 13, a saving of 13.33 percent. On performance, planned value of 100,000 against earned value of 80,000 gives an index of 0.8, while actual cost of 90,000 gives a cost index of 0.89. It ends on peak headcount and the definition of the critical path.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 |
| Suggested time | 25 |
| Difficulty mix | Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1 |
| Chapter | Chapter: S6 ICT: Project Management and Scheduling |
| Level | Intermediate (10 items) |
02 Questions (10 items)
- FoundationTasks A, B and D take 4, 6 and 5 days in series. How long is that path?
- FoundationThe same network also has a path A to C to D with C at 3 days. How long is that path?
- FoundationWhich path is critical and what is the project duration?
- IntermediateWhat is the total float of task C?
- IntermediateTask C has an earliest start of day 4. What is its latest start?
- IntermediateCrashing task B from 6 to 4 days changes the duration to what, and by what percentage?
- ChallengePlanned value is 100,000 dollars and earned value 80,000 dollars. What is the schedule performance index and what does it mean?
- ChallengeActual cost is 90,000 dollars. What is the cost performance index?
- Challenge5 tasks run at the same time, each needing 2 people. What is the peak headcount?
- Error redoError item: a student says the critical path is the shortest path in the network. What is wrong?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | 15 days. | 4 plus 6 plus 5 gives 15. |
| 2 | 12 days. | 4 plus 3 plus 5 gives 12. |
| 3 | A to B to D is critical and the duration is 15 days. | The longest path wins, and 15 exceeds 12, so the project runs 15 days. |
| 4 | 3 days. | The critical path minus the path through C is 15 minus 12, giving 3. |
| 5 | Day 7. | Working back from the finish, 15 minus 5 minus 3 gives 7. |
| 6 | 13 days, a cut of 2 days or 13.33 percent. | 4 plus 4 plus 5 gives 13; the saving over 15 is 13.33 percent. |
| 7 | 0.8, meaning the project is twenty percent behind schedule. | The index is 80000 over 100000, or 0.8; below one means slipping. |
| 8 | 0.89, so each dollar spent returns only 0.89 dollars of value. | The index is 80000 over 90000, or 0.89; below one means overspending. |
| 9 | 10 people. | 5 times 2 gives 10, which feeds resource levelling. |
| 10 | Wrong. The critical path is the longest path and it carries zero total float. | Mixing up the longest duration with the shortest path leads to crashing the wrong task. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.