S6 ICT: project management and scheduling (challenge)

S6 ICT: project management and scheduling (challenge)

  • 2026-11-20

S6 ICT: project management and scheduling (challenge)

Challenge: three competing paths, three point estimating, crash cost per day and overrun arithmetic.

Challenge: estimating and crash cost The third paper pushes scheduling into multiple paths and estimating. The three paths run 12, 9 and 7 days, so the longest A to B to E is critical at 12 days; C holds 3 days of float and D holds 5, so crashing C pays off sooner. Three point estimating with 4, 6 and 14 days gives an expected 7.0 days and a standard deviation of 1.67. Crashing 2 days for 6,000 dollars works out at 3,000 per day. A 10,000,000 dollar budget overrun by 12 percent becomes 11,200,000, and 85 percent of 20 work packages is 17. It closes on resource levelling.

01 Paper details (check answers afterwards)

Item Detail
Questions 10
Suggested time 25
Difficulty mix Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1
Chapter Chapter: S6 ICT: Project Management and Scheduling
Level Challenge (10 items)

02 Questions (10 items)

  1. FoundationA network has three paths: A to B to E at 12 days, A to C to E at 9 days and D to E at 7 days. Confirm each total.
  2. FoundationWhich path is critical and what is the duration?
  3. FoundationWhat is the total float of task D?
  4. IntermediateWhat is the total float of task C?
  5. IntermediateThree point estimating gives 4, 6 and 14 days. What is the expected duration?
  6. IntermediateWhat is the standard deviation of that estimate?
  7. ChallengeCrashing 2 days costs an extra 6,000 dollars. What is the crash cost per day?
  8. ChallengeA project budget of 10,000,000 dollars overruns by 12 percent. What is the final spend?
  9. Challenge85 percent of 20 work packages are complete. How many is that?
  10. Error redoError item: a student claims resource levelling always shortens a project. What is wrong?

03 Answers and one-line notes

# Answer One-line note
1 12, 9 and 7 days. 3 plus 7 plus 2 is 12; 3 plus 4 plus 2 is 9; 5 plus 2 is 7.
2 A to B to E, giving 12 days. The longest of the three is 12 days and its float is zero.
3 5 days. 12 minus 7 gives 5, the delay D can absorb without moving the finish date.
4 3 days. 12 minus 9 gives 3, tighter than D.
5 7.0 days. 4 plus 24 plus 14, all over six, gives 7.0.
6 1.67 days. 14 minus 4, over six, gives 1.67, which measures the spread of the estimate.
7 3,000 dollars. 6000 over 2 gives 3000, the figure used to rank crashing options.
8 11,200,000 dollars. 10000000 multiplied by 1.12 gives 11200000.
9 17. 20 times 0.85 gives 17, leaving 3.
10 Wrong. Levelling usually extends it, for example from 12 to 14 days, 2 days or 16.7 percent longer. Levelling flattens the peak demand, and the price is waiting for resources, so the schedule usually stretches.

04 What to do after marking

  • After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
  • Repeat the same item two days later; move to the next paper only when both attempts are correct.
  • Parents only need the answer and note columns; there is no need to explain every item.

Want every float value on the network diagram worked out cell by cell? Book a TutorZone tutor and unpack all ten items with the critical path in 25 minutes.Tutor Registration →

Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.

Join as a tutor or coach — academic, music, sports, arts, STEM. Free to register. See how it works →