S6 ICT: project management and scheduling (challenge)
- 2026-11-20
S6 ICT: project management and scheduling (challenge)
Challenge: three competing paths, three point estimating, crash cost per day and overrun arithmetic.
Challenge: estimating and crash cost The third paper pushes scheduling into multiple paths and estimating. The three paths run 12, 9 and 7 days, so the longest A to B to E is critical at 12 days; C holds 3 days of float and D holds 5, so crashing C pays off sooner. Three point estimating with 4, 6 and 14 days gives an expected 7.0 days and a standard deviation of 1.67. Crashing 2 days for 6,000 dollars works out at 3,000 per day. A 10,000,000 dollar budget overrun by 12 percent becomes 11,200,000, and 85 percent of 20 work packages is 17. It closes on resource levelling.
01 Paper details (check answers afterwards)
| Item | Detail |
|---|---|
| Questions | 10 |
| Suggested time | 25 |
| Difficulty mix | Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1 |
| Chapter | Chapter: S6 ICT: Project Management and Scheduling |
| Level | Challenge (10 items) |
02 Questions (10 items)
- FoundationA network has three paths: A to B to E at 12 days, A to C to E at 9 days and D to E at 7 days. Confirm each total.
- FoundationWhich path is critical and what is the duration?
- FoundationWhat is the total float of task D?
- IntermediateWhat is the total float of task C?
- IntermediateThree point estimating gives 4, 6 and 14 days. What is the expected duration?
- IntermediateWhat is the standard deviation of that estimate?
- ChallengeCrashing 2 days costs an extra 6,000 dollars. What is the crash cost per day?
- ChallengeA project budget of 10,000,000 dollars overruns by 12 percent. What is the final spend?
- Challenge85 percent of 20 work packages are complete. How many is that?
- Error redoError item: a student claims resource levelling always shortens a project. What is wrong?
03 Answers and one-line notes
| # | Answer | One-line note |
|---|---|---|
| 1 | 12, 9 and 7 days. | 3 plus 7 plus 2 is 12; 3 plus 4 plus 2 is 9; 5 plus 2 is 7. |
| 2 | A to B to E, giving 12 days. | The longest of the three is 12 days and its float is zero. |
| 3 | 5 days. | 12 minus 7 gives 5, the delay D can absorb without moving the finish date. |
| 4 | 3 days. | 12 minus 9 gives 3, tighter than D. |
| 5 | 7.0 days. | 4 plus 24 plus 14, all over six, gives 7.0. |
| 6 | 1.67 days. | 14 minus 4, over six, gives 1.67, which measures the spread of the estimate. |
| 7 | 3,000 dollars. | 6000 over 2 gives 3000, the figure used to rank crashing options. |
| 8 | 11,200,000 dollars. | 10000000 multiplied by 1.12 gives 11200000. |
| 9 | 17. | 20 times 0.85 gives 17, leaving 3. |
| 10 | Wrong. Levelling usually extends it, for example from 12 to 14 days, 2 days or 16.7 percent longer. | Levelling flattens the peak demand, and the price is waiting for resources, so the schedule usually stretches. |
04 What to do after marking
- After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
- Repeat the same item two days later; move to the next paper only when both attempts are correct.
- Parents only need the answer and note columns; there is no need to explain every item.