S6 ICT: project management error rework

S6 ICT: project management error rework

  • 2026-11-20

S6 ICT: project management error rework

Ten common scheduling misconceptions, each corrected with one line of explanation.

Error rework: ten common slips This paper lists ten common misconceptions: the critical path as the shortest path, zero float as free slippage, milestones with duration, a Gantt chart that cannot show links, a WBS that is always better deeper, crashing that saves money, float as unlimited room, levelling that shortens a project, ninety percent done leaving ten percent of the effort, and compression working on any task. Each item names the error, gives the correct rule and adds one line of explanation, which also serves as a check on your own revision notes.

01 Paper details (check answers afterwards)

Item Detail
Questions 10
Suggested time 25
Difficulty mix Foundation 3 · Intermediate 3 · Challenge 3 · Error redo 1
Chapter Chapter: S6 ICT: Project Management and Scheduling
Level Error rework (10 items)

02 Questions (10 items)

  1. FoundationError item: the critical path is the shortest path in the network. What is correct?
  2. FoundationError item: zero float means the task can slip freely. What is correct?
  3. FoundationError item: milestones need duration and staffing. What is correct?
  4. IntermediateError item: a Gantt chart cannot show task dependencies at all. What is correct?
  5. IntermediateError item: the deeper a WBS is broken down, the better. What is correct?
  6. IntermediateError item: crashing always shortens the schedule and saves money. What is correct?
  7. ChallengeError item: any task with float can be delayed without consequence. What is correct?
  8. ChallengeError item: resource levelling automatically shortens the schedule. What is correct?
  9. ChallengeError item: at ninety percent complete only ten percent of the work remains. What is correct?
  10. Error redoError item: compressing any task shortens the project. What is correct?

03 Answers and one-line notes

# Answer One-line note
1 The critical path is the longest path and has zero total float. The longest path sets the finish date, so the wrong choice crashes the wrong task.
2 Zero float means the task is critical and one day of slip delays the whole project. Float is the allowance for delay, so zero allowance leaves no room.
3 A milestone has zero duration and serves only as a checkpoint, consuming no resources. Treating a milestone as a task inflates the schedule for nothing.
4 A Gantt chart shows finish to start links with arrows, and a network diagram is used when links become dense. The two views serve different purposes: Gantt for time, network for logic.
5 A work package is usually sized at 8 to 80 hours; over splitting only adds management cost. Too fine a breakdown makes reporting and control heavier than the work itself.
6 Crashing trades money for time and only works on the critical path. Crashing a non critical task just adds float without moving the finish date.
7 Only within its total float; beyond that it pushes the next task and the finish date. Free float protects the next task while total float protects the finish date.
8 Levelling flattens peak demand and normally lengthens the schedule, for example from 12 to 14 days. The aim is steady resource use, not time compression.
9 Integration and acceptance often dominate the tail, so the last tenth can take over thirty percent of the effort. This is the ninety percent rule: the closer to done, the harder the remainder is to estimate.
10 Only compressing tasks on the critical path shortens the project; the rest merely gain float. Whether time can be won depends on whether the task total float is zero.

04 What to do after marking

  • After marking, redo only the wrong items and write down which step went wrong (formula, unit, or misread number).
  • Repeat the same item two days later; move to the next paper only when both attempts are correct.
  • Parents only need the answer and note columns; there is no need to explain every item.

Want every float value on the network diagram worked out cell by cell? Book a TutorZone tutor and unpack all ten items with the critical path in 25 minutes.Tutor Registration →

Questions and answers are written originally by the TutorZone team and are not taken from any school, publisher or examination authority paper. Every value is checked by computer.